Date de publication : 12 April 2024
Update on road work: April 2024
Here’s a look at what’s on and what’s coming up for the Public Works team:
Please note that street sweeping (Mansonville and Owl’s Head sectors) has been moved up to this Saturday, April 27, 2024.
UPDATE APRIL 26, 2024 :
- Grading work scheduled for April 26 in the Leadville sector
- Grading work scheduled for April 26 or the week of April 29 in the Bombardier sector
- Work on Miltimore culverts
UPDATE APRIL 19 :
- Grading work completed on Province Hill, Bellevue, Bombardier and George-R.-Jewett.
- Grading begins on Peabody today, April 19
- Next roads to be graded: de-l’Étang-Sugar Loaf, Schoolcraft and Traver
- Culvert replaced on Province Hill
UPDATE APRIL 12:
- Preliminary spring grading began this week on West Hill, Bellevue and de l’Aéroport roads;
- Grading on Peabody, de-L’Étang-Sugarloaf, Schoolcraft and Traver roads during the week of April 15, weather permitting;
- Minor repairs on Laplume Road scheduled for the week of April 15;
- Minor repairs on Leadville Road at Owl’s Head Road during the week of April 15;
- Culvert replacement on Cheminots at civic address 63 during the week of April 15 or 22;
- Culvert replacement on Province Hill Road at civic address the week of April 15 or 22;
- Cleaning of ditches on Bombardier Road during the week of April 22.
*This page will be updated weekly this spring.